by Dependable Construction | Jul 4, 2018 | Commercial, Drywall, New Construction, Remodeling
Run the mud and laying the tape is moving right along but with the humidity being so high it’s going to go slow. Thankfully they have a handful of add-ons they want done.
#dcandr #drywall #dependabilityfirst #finishing #construction #decamiddle #commercialproject
by Dependable Construction | Jul 4, 2018 | Doors, Drywall, New Construction
Where this once was a door, a door no more. There really was no point in having to doors feet from each other that both lead into the same classroom.
#dcandr #drywall #dependabilityfirst #door #construction #decamiddle #commercialproject
by Dependable Construction | Jul 4, 2018 | Commercial, Drywall, New Construction, Remodeling
All the drywall has also been hung on the fourth floor and is ready to get some mud on it. These two floors are humid so this may take some time.
#dcandr #drywall #dependabilityfirst #finishing #construction #decamiddle #commercialproject
by Dependable Construction | Jul 4, 2018 | Drywall, New Construction, Remodeling
All the drywall on the third floor has been hung and all inspection have been passed. It’s time to throw some mud and get to finishing.
#dcandr #drywall #dependabilityfirst #finishing #construction #decamiddle #commercialproject
by Dependable Construction | Jul 3, 2018 | Drywall, Framing
The drywall is also hung on the back side of the second floor’s new classroom. The inspector is upstairs viewing that one but this was approved and is ready for insulation and new drywall.
#dcandr #drywall #decamiddle #dependabilityfirst #framing #comingtogether #construction
by Dependable Construction | Jul 3, 2018 | Drywall, Framing
Drywall is up on the back side of the 4th floor classroom, now were are just waiting on the framing inspector to get here and sign off on it so we move on to the insulation and drywall on this side.
#dcandr #drywall #decamiddle #dependabilityfirst #framing #comingtogether #construction